Two Walton County projects will change how Miramar Beach gets to the water, one on the Gulf side and one on the bay side. Both are paid for with South Walton tourist development tax money, and both appear on the same county reserve sheet. As of this month, the county has set a finish date for only one of them.
The Driftwood Road Beach Park and Ride has a contract completion date of December 27, 2026. Legion Park, on Crest Drive, has a finished design, conditional approval, and $1.675 million set aside in reserve. Its status is still "Pending Final Permit Approval," and the county has not given a start date. The Driftwood lot is a construction job that fell behind and got more time. Legion Park is held up by permit conditions about the land itself.
The Driftwood lot's December date came from a stop-work order
The parking facility at 76 Driftwood Road was not originally supposed to finish in December. Here is how it got there, according to county records:
- June 17, 2025. Walton County broke ground on the facility. It described the lot as extra parking for Miramar Regional Beach Access, about a quarter-mile south, with sidewalks and pedestrian-safety work included.
- The contract. Elite Building Group won the job with a bid of $2,210,719.12. The original contract gave the builder 300 days from the notice to proceed to reach substantial completion, then up to 30 more days after the county issued its punch list to reach final completion.
- October 8, 2025. The county stopped work because the contractor had used an unacceptable aggregate in the exfiltration system, the underground part of the stormwater setup. County staff and the contractor then worked out a corrective plan.
- June 9, 2026. The Board of County Commissioners passed a 243-day extension on its consent agenda without objection. The contract price did not change, and the new completion date became December 27, 2026.
- October 6, 2026. At the Tourist Development Council meeting, the county reported the project 35% complete, with completion expected in winter 2026.
That puts the job about a third done with roughly eleven weeks left on the contract. The finished facility will have 82 parking spaces, four EV charging stations, an 800-square-foot restroom building, ADA, LSV and bicycle parking, and drainage improvements. It will also serve as a hub for the South Walton Beach Tram. People could park on the Driftwood parcel before construction, but it had no marked spaces and no amenities.
What the new lot adds to parking at 2375 Scenic Gulf Drive
Miramar Regional Beach Access at 2375 Scenic Gulf Drive already has a sizable lot. The county's beach access chart lists 138 spaces in the main lot and 62 in the north lot, and the county's Miramar Park page says parking there is free. The Driftwood lot adds 82 spaces to that base. It also brings something Miramar Beach doesn't have yet, which is the tram.
Today, the free Beach Tram runs only out of the 393 and Grayton Beach park-and-rides, serving the accesses from Dune Allen east to Grayton. The county's transportation page lists Driftwood Road as "Coming Soon." It says the lot will get a direct route to Miramar RBA and to other accesses along Scenic Gulf Drive, with "final routes coming soon." When the expanded routes started on March 1, WMBB reported that Driftwood would become a third pickup location once construction was done. County transportation manager Tabatha Bolen told the station that the Grayton lot alone moved "a quarter of a million riders" in a year on four trams. The county hasn't announced a Driftwood launch date or a full list of stops.
It also hasn't said whether Driftwood will charge for parking. The county's other park-and-rides started a paid program on April 3, 2026, covering the Van Ness Butler, County Road 393 and Grayton Beach lots. WJHG reported the rates as $15 a day or $5 an hour, with an annual permit of $5 for Walton County residents and $205 for non-residents. The tram stays free from all of those lots. Driftwood's fee will be one of the details the county announces closer to opening. The main lot at Miramar RBA wasn't part of the paid rollout, and no fee change has been announced for it.
Legion Park's design is finished. The conditions aren't met yet.
Legion Park covers about 3.43 acres on the north side of Crest Drive, east of North Geronimo Street. According to the county's facility listing, it currently has basketball goals, boat and canoe access, parking, a pickleball court, picnic areas, a playground and restrooms.
The county's plan keeps all of those uses and makes each one bigger or newer. As presented to the county's Technical Review Committee on February 4, 2026, the plan includes:
- A splash pad, which the October update lists at 20 feet across
- New playground equipment to replace the old set
- The existing pickleball court moved to a more central spot closer to Crest Drive, plus a second court
- The existing basketball court removed and replaced, and the volleyball court removed
- Two shaded pavilions
- Two piers along the boat ramp
- A paved driveway and parking areas, new sidewalks, irrigation and landscaping
Public comment at that meeting covered stormwater, noise, wildlife habitat, trees, open space and boat-launch safety. It also included support for upgrading the courts and the playground.
The design team from Barge Design Solutions described the changes made in response. Seven trees would be removed, one of them an invasive species, and eight new trees planted. Larger-caliber trees would be planted around the relocated courts to buffer sound. The splash pad would recirculate treated water, irrigation would run on a well, and no additional dredging was planned for the boat access.
According to the committee minutes, the committee found that the project met the technical requirements of the land development code and approved it 3-0, with two conditions. The county must deal with any historical or archaeological resources on the site, and it must provide a narrative addressing older deeds, possibly tied to the Bureau of Land Management, that may limit development there. The chair also noted that any future vendor operations at the park would need county commission approval at a public hearing.
Eight months later, the October 6 update still lists the project as "Pending Final Permit Approval."
Same reserve account, different hold-ups
The October TDC financial report shows that money is not what's holding Legion Park back. The county's capital reserves for Miramar Beach include three separate lines:
| Reserve line, Oct. 6, 2026 TDC report | Amount | Where it stands |
|---|---|---|
| Driftwood Parking Facility | $1,645,000 | Under construction, 35% complete, contract ends Dec. 27, 2026 |
| Legion Park Repairs | $1,675,000 | Pending final permit approval, no contract awarded, no start date |
| Miramar Beach Parking Facility | $7,000,000 | Separate 4.5-acre parking project, no current design published |
Legion Park's reserve is about the same size as the money still held for Driftwood. A reserve isn't a construction award or a final cost, but it does mean funding is already set aside for when permitting clears. Driftwood's delay was a materials problem underground, and the fix was more time at the same price. Legion's remaining questions are about deeds and possible archaeological resources, and no contractor can resolve those.
The third line is the furthest out. County records describe a separate 4.5-acre Miramar Beach parcel intended for beach parking, with its development folded into design and permitting for the Driftwood Road–Ellis Road corridor. County tourism material places that project off US 98. The county's 2026–30 capital plan puts $500,000 toward it in FY2026 and $6.5 million in FY2027. An earlier county document, the 2021 Miramar and Sandestin Transit Mobility Hub Plan, proposed a hub of more than 200 spaces east of Ellis Road that could eventually become a parking structure if demand called for it. The records reviewed for this post don't confirm that the 2021 concept is the current project, and they don't give a current capacity, design or start date for it.
Over the next few months, three things will show whether the Driftwood timeline is holding. The first is a percent-complete figure in the TDC's monthly director update that moves faster than it did through the stop-work period. The second is a posted list of Scenic Gulf Drive tram stops on the county transportation page. The third is a parking-fee announcement for 76 Driftwood Road. For Legion Park, the next step will be a final permit, followed by a construction award on a county commission agenda. Neither has happened yet.
If county projects like these are shaping how you think about a property near Scenic Gulf Drive or Crest Drive, whether that's beach parking, tram access or the park nearby, The Gettings Group follows these agendas closely and would be glad to talk through what they mean for a specific street. Work With Us.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.